ENVIRONMENT

Heritage issues hits Rio Tinto iron ore output

Still suffering from Juukan Gorge blast.

The Juukan Gorge rock shelters just prior to their blasting last year.

The Juukan Gorge rock shelters just prior to their blasting last year.

Pilbara iron ore production of 75.9 million tonnes was 9% lower than the 2020 second quarter and Rio Tinto believes its iron ore shipments will be at the low end of the full-year guidance range of 325 million tonnes to 340Mt.

Above average rainfall in the west Pilbara also had an impact. That is estimated to have had about a 3Mt impact on the first half.

Operating costs for Pilbara iron ore have also risen to $18-$18.50 per tonne, up from $16.70-$17.70/t.

Rio Tinto has committed to focus on rebuilding the relationships in the Pilbara it blew up along with two 46,000 year old rock shelters considered sacred by the Traditional Owners the Puutu, Kunti, Kurrama and Pinikura peoples.

Rio Tinto has committed to focus on rebuilding the relationships in the Pilbara it blew up along with two 46,000 year old rock shelters considered sacred by the Traditional Owners the Puutu, Kunti, Kurrama and Pinikura peoples.

A key focus of those efforts will be for Rio Tinto and the PKKP to determine an appropriate remedy for the destruction of the Juukan Gorge shelters.

Some rehabilitation works around the shelters have already been done.

Some of those relationship rebuilding efforts are impacting on some of its operations.

Known sites of cultural significance in and around Rio Tinto operations have been reassessed. Mine plans have been adjusted and measures taken to avoid disturbance. In some cases buffer zones have been increased.

Blast management plans have been developed to create smaller, higher controlled blasts to minimise vibration and protect heritage sites. That affected about 11% of blasts in the first half.

Rio Tinto is also working on creating greater opportunities for Indigenous businesses in WA and beyond.

In the first half of 2021 it increased procurement with Indigenous vendors by about 40% compared with the first half of 2020.

Rio Tinto's Indigenous Business Development plan is expected to be finalised in July and engagement with Pilbara Indigenous businesses has begun.

Shutdowns to enable replacement mines to be tied in at Western Turner Syncline and Robe Valley, and reduced processing plant availability, particularly at Yandicoogina, had about a 4Mt impact on the half.

Execution of those shutdowns was also impacted by labour shortages due to COVID-19 restrictions and high labour demand.

On the replacement mines front, mining has begun at Gudai-Darri, Rio Tinto's first iron ore hub in more than five years, with more than 9 million cubic metres of pre-stripping completed in June.

Labour shortages have impacted both steel fabrication and site construction activities.

First Gudai-Darri ore in the crusher is expected in 2021, although commissioning is later than originally planned. The project is still expected to ramp up in early 2022.

At West Angelas (C,D), first ore was achieved in June with load commissioning expected later in the year. That was impacted by delays related to heritage management.

First ore at the Robe Valley (Mesa B, C, H) and Western Tyrner Syncline Phase 2 replacement projects is still expected in 2021.

Rio Tinto admits some mine production risks remain in the second half of 2021 as it finishes building and commissioning Gudai-Darri and ramps up production from the other replacement mines.

In June Rio Tinto completed a five-week maintenance shut at its East Intercourse Island port terminal slightly ahead of plan.

The shut was to replace four apron feeders below the rail car dumper that were about 50 years old.

The increased tightness in WA's labour market is continuing, in particular in shortages of relating to structural, mechanical, electrical and instrumentation disciplines. That is being exacerbated by ongoing COVID-19 travel restrictions.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions