Slower than expected transition to Macmahon impacts Gwalia production.

The slower than expected transition to a new contractor at Gwalia has impacted St Barbara's guidance.

The slower than expected transition to a new contractor at Gwalia has impacted St Barbara's guidance.

The slow transition, along with lower grades going to the Leonora mill and labour shortages have forced St Barbara to downgrade its 2020-21 guidance from 175,000 ounces to 150,000-160,000oz at an all-in sustaining cost of $1815 per ounce to $1950/oz. It had previously forecast FY21 AISC of $1590-1630/oz.

The Leonora mill's throughput remained above nameplate capacity of 1.2 million tonnes per annum and development advance rates were sustained at more than 400m for the third consecutive month.

However, the lower grades going to the mill helped cause the downgrade.

St Barbara made the decision to change underground mining contractor at Gwalia from Byrnecut to Macmahon and that change took effect from May 5. It believed restructuring the mining contract and strategy delivered a "compelling business case for the future of Gwalia".

The transition was slower than expected though and Macmahon has struggled to recruit critical roles and experienced operators for the work.

"While St Barbara continues to work with Macmahon, WA-based workforce availability has ultimately impacted the mine schedule and has led to the deferral of mined ore tonnages from FY21 to FY22," St Barbara said in a statement to the Australian Securities Exchange.

The miner has also suffered setbacks at its Simberi gold mine in Papua New Guinea.

Operations there continue to be hampered by ore variability due to low mining rates not achieving planned face positions, which is affecting gold recovery.

COVID-19 is another big factor in PNG, affecting the availability of workers.

Managing the virus at Simberi is putting pressure on the operation and its workforce.

St Barbara has downgraded its FY21 guidance for Simberi to 80,000-90,000oz. It had previously expected to reap 95,000oz from the operation.

The Simberi AISC has also risen to between $1790/oz and $2030/oz from $1720/oz-$1810/oz.

The only positive for St Barbara has been the unchanged expectations at its Atlantic operations centred on a Nova Scotia, Canada gold mine.

FY21 guidance there remains unchanged at between 100,000oz and 110,000oz and AISC between $958/oz and $1050/oz.

The overall picture for St Barbara is that its consolidated FY21 guidance is forecast to be 330,000-360,000oz, down from 370,000-380,000oz. The overall AISC has also risen to $1547-$1694/oz from $1440-$1520/oz.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production