THE federal government has approved GVK-Hancock's $6.5 billion Alpha thermal coal project in Quee...

Lou Caruana

This article is 12 years old. Images might not display.

Indian giant GVK welcomed the government’s decision, which came after Burke said he would “stop the clock’ on the approval process because he believed Queensland’s handling of it was “shambolic”.

“Ultimately, we believe the overall assessment process has resulted in best practice environmental protection outcomes," chairman GVK Reddy said.

Alpha, which will export 30 million tonnes per annum using a 495km rail link to Abbot Point, was controversial because it was claimed that it would endanger the Great Barrier Reef.

Burke said the approval has been granted with 19 strict conditions directed specifically at ensuring matters of national environmental significance are protected, including the Great Barrier Reef.

"My approval follows a rigorous assessment process after I was forced to step in and complete the assessment. This has ensured the highest standards of environmental regulation were applied to this project,'' he said.

"While the decision has taken an additional three months since the Queensland coordinator general's report was released, I'm satisfied that we have now put in place the required additional conditions for the protection of the environment including the Great Barrier Reef.

"I was determined to ensure that the risks to the environment such as impacts on threatened species, threats to the Great Barrier Reef and the potential for coal dust impacts and runoff were properly dealt with.

"My approval conditions have been set to address these concerns including a higher quantity of offsets for impacts on threatened species, and ensuring that industry best practice is adhered to and that strict threshold limits for coal dust impacts on the reef are met through the provision of covered wagons or equivalent and in the Caley Valley management plan.”

Burke said he ensured that management plans were put in place to ensure stormwater and runoff or coal dust impact from the project is managed to minimise sediment into the Burdekin Dam and onto the Great Barrier Reef.

"My decision has been based on a thorough and rigorous assessment of the proposal taking into account the advice of my department and independent scientific advice,” he said.

"While I have considered the social and economic implications of this project, my focus has been on protecting matters of national environmental significance through strict conditions, including a significant offsets package.

"In making this decision I took advice from members of the interim independent expert scientific committee on coal seam gas and coal mining, which made recommendations related to groundwater impacts in the Galilee Basin and surface water impacts in the Burdekin catchment."

Queensland Deputy Premier and Minister for State Development, Infrastructure and Planning Jeff Seeney called on the federal government to move quickly on the approvals process for the South of Embley mine after the Alpha coal project approval.

"Mr Burke said today he had no other Queensland projects on his desk. Well, South of Embley has been sitting there since May 23 when Queensland approved it," Seeney said.

"The federal minister has taken that mine back to square one in the approvals process based on misinformation about shipping movements supplied to him by the greens movement.”

The Queensland coordinator general approved the Alpha project and sent his approval to the federal minister on May 31, Seeney said.

"It has taken 59 business days since then for the federal government to give its approval – a relatively short timeframe for the Commonwealth which has taken more than 500 business days to make a decision in previous instances," he said.

The Commonwealth EPBC Act provides 30 business days for the federal decision-making process.

“This government will continue to work with industry, we will continue to get good environmental outcomes and good employment outcomes for Queensland, but no matter how many times you ask, if you want to indulge in environmental corner cutting, shambolic process and environmental vandalism, we will have none of it,” Burke said.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence: Future Fleets Report 2025

MMI Future Fleets Report 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.