GEOLOGICAL challenges at Yancoal Australia's Austar underground mine continued to affect the oper...

Lou Caruana

This article is 10 years old. Images might not display.

A New South Wales Mine Safety Unit investigation into the wall collapse at Austar that killed two miners is examining its design, the incident site geotechnical conditions, and the suitability of engineering and strata controls.

The previous redeployment of Austar development crews to the Abel and Ashton mines in April 2014 was determined unsustainable during the period, with all three operations subsequently restructured in an effort to improve operational efficiencies and reduce costs.

The restructure of the Abel mine resulted in an improved production performance, up 9% on the previous quarter, despite challenging geological conditions experienced in the main workings.

Equity share saleable coal production for the company was 4.39 million tonnes, down 1% on the previous quarter, and down 1% year-on-year.

With the Stratford operation having reached the end of its economically recoverable reserves, Yancoal remains focused on achieving approval for the proposed Stratford expansion project. If approved, the expansion will provide a further 21.5Mt of ROM coal over 11 years.

Combined production for the Stratford and Duralie mines was down 13% on the previous quarter, in accordance with production expectations.

The NSW Planning Assessment Commission approved the Duralie modification in December 2014, providing increased flexibility in mine planning and sequencing and enabling the extraction of the fully approved reserve.

In Queensland, Yarrabee maintained its strong performance throughout the period, up 20% on the previous quarter. Productivity improvements at Yarrabee and the restart of longwall production at Ashton drove saleable coal production for the quarter.

Ashton’s restart of longwall production following a scheduled move drove gains, up 190% on the previous quarter.

During the period, Yancoal also secured 100% ownership of the Ashton operation, purchasing former joint venture partner ICRA Ashton Pty Ltd’s 10% holding in October.

The NSW Land and Environment Court granted approval to the Ashton southeast open cut project, subject to conditions, in December.

Moolarben’s product optimisation strategy introduced in the September quarter continued to generate steady production throughout the December quarter.

During the quarter Moolarben also concluded arrangements to secure access to all remaining land required for the future development of the Moolarben stage two project, if approved.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions