Missing policies, worker error led to fatality: MSHA

AN investigative report by the US Mine Safety and Health Administration is pointing to missing pr...

Donna Schmidt

This article is 14 years old. Images might not display.

Ray Oney was working for Virginia contractor Coalfield Services on mine fan construction at M-Class Mining’s MC No. 1 mine in Franklin County, Illinois on April 11 when a machinery incident occurred.

“The victim and three other Coalfield employees were working to attach a 16-foot-long section of stairs to the side of the mine fan housing [and] the victim was standing at the bottom of the stair stringer holding onto the handrails,” the agency explained.

There were two nylon slings attached between the hook on the truck-mounted crane and the bottom of the stair stringer, the latter of which needed to be lifted so that a timber could be removed.

When the crane listed the stairs, the top of the stringer began to slide as the bottom end shifted away from the fan housing where the stringer was situated and toward the victim.

“The stairs forced the victim backward against the frame of the articulating boom manlift that was parked directly behind him. The bottom of the stair section struck the victim in the chest as he was against the manlift.”

Eyewitnesses said Oney walked approximately 10 feet from the accident location just after the event and fell to the ground. He was pronounced dead at a local hospital at 4.30pm local time, about an hour after the incident.

“The accident occurred because employees failed to stay clear of hoisted loads,” MSHA investigators said in the report.

“In addition, a contributing factor to the accident was the method used to temporarily attach the stair stringer to the air duct. The method was not sufficient to support the weight of the stair stringer and hold it in place.”

Federal officials said the policies and controls in place at the MC No. 1 construction site did not ensure that workers would stay clear of hoisted loads.

To rectify the issue, all employees were trained on proper hoisting and rigging procedures and were instructed to stay clear of hoisted loads.

Additionally, Coalfield Services submitted a written statement to the MSHA district manager outlining stair installation procedures to be followed going forward.

Two citations were issued by federal investigators, one 104(a) to Coalfield Services citing

30 CFR Section 77.210(b) and one 104(a) to M-Class Mining, citing the same regulation.

The MC No. 1 mine was under construction and in non-producing status at the time of the accident.

Coalfield Services was hired to install an emergency escape hoist in the intake side of the dual compartment air shaft and to install the air duct on the exhausting (return) side of this shaft.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence: Future Fleets Report 2025

MMI Future Fleets Report 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.