Whitehaven grapples with Werris Creek geotech issues

RUN-of-mine production from Whitehaven Coal’s Werris Creek open cut mine in New South Wales plunged 37% in the March quarter due to a geotechnical failure that occurred in late February.

Werris Creek has been focused on geotechnical remediation.

Werris Creek has been focused on geotechnical remediation.

RoM coal production was 300,000t for the period as the mine focused on geotechnical remediation, which restricted mining progression and delayed the release of RoM coal. Werris Creek's RoM coal production...

Start a free trial to continue reading this article

Already have an account?

Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions