UNDERGROUND

Abra taking shape

The decline is 250m vertically below the surface and 13m vertically below the top of the orebody.

 Processing plant with completed TSF and village in background. Photo taken October 14, 2022.

Processing plant with completed TSF and village in background. Photo taken October 14, 2022.

Galena Mining managing director Tony James said construction was 87% complete at Abra, a 60:40 joint venture in WA's Gascoyne with Japan's Toho Zinc.

"It's both exciting and extremely rewarding for everyone involved to see several areas progressing quickly into commissioning at the mine," he said.

"With the site power station, power-on scheduled for the second half of October, the processing plant commissioning plans have been finalised and these plans will be executed at the same time and then continue to roll through to January."

James said process plant engineering, procurement and construction had reached 93% complete while structural steel was 98% complete.

Mechanical installation was 73% done and piping and electrical works were 48% and 36% complete respectively.

Commissioning of the Pacific Energy hybrid liquid natural gas-solar power station was also nearly finished, with dry commissioning of the crushing and screening areas in the processing plant to start in the second half of October.

James said the focus was on finishing the processing facility and underground development of the mine, which accounted for $19.2 million of the remaining budget forecast of $30.6 million.

"Record development metres underground in September has taken us down to the top of the orebody and work has started on the first access drives," he said.

"In recent days the completion of the first stage of the tailings storage facility is also a significant milestone."

Mine decline development in the East decline hit 285m to reach the 1300m level.

This was the highest level of development in a month since the first cut was fired in the portal in 2021.

The decline is 250m vertically below the surface and 13m vertically below the top of the orebody.

James said grade control and infill diamond drilling continued during September with the introduction of a second underground drill.

 

/

Image of some of the spectacular galena mineralisation being seen in the underground grade control and infill drilling program.

 

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production