MANAGEMENT

Old gold from Norseman works

Tulla wants to resume production at the iconic Norseman gold project.

 Norseman gold project

Norseman gold project

The old ore is on the mine's run-of-mine pad for processing in the future.

With relevant approvals in hand Tulla kicked-off construction of a 1 million tonne per annum CIL plant by firstly demolishing the old plant.

Demolition and site clean-up works are complete and the site ready for immediate construction, with contractor GR Engineering Services already mobilised for the start of the build.

Construction workers are being accommodated in a co-living village in Norseman owned and operated by Resource Accommodation Management.

Tulla shares a 50% interest in the Central Norseman gold project with Pantoro.

The historic gold project in Western Australia's Goldfields has produced more than 5.5 million ounces of gold since 1935.

The 50-50 joint venture is keen to exploit the project's known resource of 21 million tonnes graded at 3.4 grams per tonne for 2.3Moz, and attributed ore reserve of 357,000oz - on a 50% basis.

Tulla executive chairman Kevin Maloney said construction of the plant marked an exciting milestone for the company on the critical path to resume production at the iconic Norseman gold project.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets