BMA ditches Leighton at Peak Downs

THE BHP Billiton Mitsubishi Alliance has ditched a pre-strip contract with Leighton Contractors a...

Lou Caruana
BMA ditches Leighton at Peak Downs

Leighton Contractors will cease operating at Peak Downs on July 3, 2013.

It estimates the maximum impact of the reduction of work in hand over the two years to 2015 is approximately $260 million.

“Against a backdrop of increasing costs and falling commodity prices, BMA continues to focus on reducing its overheads and operating costs across the business,” a BHP spokeswoman told ILN.

“This includes reviewing contractor arrangements and making the necessary adjustments to ensure operations can remain cost-competitive.”

Leighton Contractors will be entitled to compensation for early termination.

It is understood that BMA will work with Leighton contractors to transition to arrangements with a pre-strip contractor HSE Mining.

BHP Billiton is running a ruler over all its coal mines in a bid to rein in costs.

It has up to $US25 billion of non-core assets it could sell, according to research by Deutsche Bank.

“BHP Billiton confirms that consistent with our commitment to simplify the portfolio, we continue to selectively pursue asset divestment opportunities, with a firm focus on value,” a BHP spokeswoman said.

“Any decision to divest an asset will be announced to the market as required.”

BMA has already started pruning its Queensland portfolio with the decision to offload the depleted Gregory mine, while keeping its options open to develop or sell the adjacent Crinum underground mine.

The conveyor gantry at Crinum South has been partially dismantled prior to relocation to Gregory to feed the Crinum East product.

HSE Mining (formally known as Howard Springs Earthmoving) is a privately owned Australian company established in the Northern Territory in 1991.

Its head office is in Perth and it has branch offices in Queensland.

HSE Mining has grown rapidly since its formation and owns a fleet of more than 150 specialised machines.

It was recently awarded a five-year pre-stripping contract by BMA at the Saraji minesite in central Queensland.

The pre-stripping operation involves the annual excavation of 42 million bank cubic metres of overburden ahead of BMA’s coal mining operations.

HSE has mobilised a number of excavator and truck fleets to the site and currently has 360 employees onsite.

HSE also has a pre-stripping contract with Ensham Resources in Emerald in Queensland and is working on the next seven-year mine life plan for the pre-stripping fleet onsite.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets