Peabody Energy has hit a snag in its development of the $US2 billion Prairie State coal-fired generating project in Washington County, Illinois, after the US Environmental Protection Agency (EPA) Environmental Appeals Board last week ordered the Illinois EPA to review its go-ahead on the project.

Angie Tomlinson
Spanner in Prairie works

The Appeals Board said the Illinois EPA had not given the public sufficient opportunity to comment prior to the final ruling earlier this year.

On January 17, the Illinois EPA awarded the plant a prevention of significant deterioration permit.

"It appears to be a procedural issue regarding the state, and we would expect to resolve it in a timely manner," a Peabody spokeswoman told Platts.

The 1500MW plant will be fueled by six million tons of coal produced each year from an adjacent mine. Construction is planned for later this year.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions