Narrabri longwall problems lead to Whitehaven production downgrade

FLOOR horizon control issues at the tailgate end of the longwall face-line at Whitehaven Coal's N...

Lou Caruana
Narrabri longwall problems lead to Whitehaven production downgrade

It has been downgraded from 10.7 million tonnes to 9.8-10Mt.

Changing conditions have led to a revision of a recovery plan timetable, which now envisages a return to longwall production in two to three weeks.

Whitehaven CEO Paul Flynn said: “We are confident that the recovery plan currently being executed will deliver a return to production in the indicated timeframe.

“All necessary resources have been committed to resolving the issue expeditiously and the Narrabri team is being supported by the appropriate external service providers.”

Mining in the third longwall panel at Narrabri started on schedule early last month and was ramped up to full production.

The configuration of longwall panel three installation differed to that of longwall panels one and two, in that two additional roof supports were added to the tailgate end of the longwall.

This modification was made to improve safety and reduce costs by eliminating the need to install additional secondary support in the tailgate roadway as had been installed in longwall panels one and two.

As the longwall retreat progressed with this revised configuration, the floor horizon control at the tailgate end of the longwall face-line was “lost”, resulting in a difference between the floor levels of the longwall face-line and the tailgate development roadway.

At this point, management decided to stop production.

Following an evaluation of the status of the longwall by management, external advisers and OEM support, a recovery plan was developed and implemented.

It was expected that the recovery plan would be completed safely within a timeframe so as not to impact the company’s ability to meet forecast ROM production of 5.5Mt (100% basis) from the Narrabri mine. However, with the revised recovery plan, Narrabri’s ROM coal production on a 100% basis for FY2014 has been reforecast to be in the range of 4.8-5Mt.

The costs of the recovery plan are not expected to be material, the company said.

“Appropriate controls to mitigate a recurrence of this event have been implemented and discussions are continuing with the longwall supplier about control systems for consistent horizon control when cutting the tailgate end of the longwall face.”

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production