MARKETS

Glencore to shut West Wallsend early

GLENCORE will close the West Wallsend longwall mine in New South Wales in mid 2016 - considerably...

Blair Price
Glencore to shut West Wallsend early

The move comes even though the mine won state government approval in October to mine two additional longwall panels, LW51 and LW52.

They equated to 2.55 million tonnes run of mine – a little less than the estimated 3Mt ROM that the mine was no longer going to extract following the subsidence impacts the mine was blamed for in the Sugarloaf state conservation area.

At the time these two panels were considered enough to not alter West Wallsend’s existing mine life or approved production capacity of 5.5 million tonnes per annum ROM, with the panels selected after the adjacent Newstan Colliery terminated a sublease.

However, Glencore has also considered market conditions when re-assessing West Wallsend’s mine life.

“The decision is consistent with West Wallsend’s life of mine planning,” the mining giant said.

“Consideration had been given to a number of options to extend the mine’s life but a combination of factors, especially coal market and economic conditions, do not support continued operations.”

Glencore also claimed the closure was only a little earlier than previously planned.

“The closure will also occur some months earlier than originally scheduled, following Glencore’s decision not to mine an approved longwall block (Longwall 47) beneath cliff lines, terraces and steeper sections of the Sugarloaf State Conservation Area.

“As a result, development work at the mine will be completed by the end of June this year, with all mining to end in mid-2016.”

A Glencore spokesman clarified that the final panel, LW52, would be completed in mid-2016.

“Naturally, there will be a period afterwards for removal of equipment etcetera and an environmental team will remain at site post-closure,” he told ICN.

At least some of the West Wallsend workforce will have opportunities to pursue employment at other Glencore coal sites.

“We always investigate options for redeployment where possible,” the spokesman said.

“This will be the case for West Wallsend.”

The end of West Wallsend accounts for a significant portion of the Glencore’s plans to cut 15Mtpa of production across its Australian coal mining complexes in 2015, which after the West Wallsend closure, will be reduced to 12 across Queensland and NSW.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production