MARKETS

West Wallsend longwall abandoned

GLENCORE has given up hopes of salvaging the longwall equipment at the West Wallsend mine in New ...

Blair Price
West Wallsend longwall abandoned

“Glencore has decided that mining on the current longwall [LW46] at West Wallsend underground operations will not continue following geotechnical issues that stopped production late last month,” Glencore said in a statement sent to International Coal News.

“The decision not to recover the longwall equipment on LW46 follows a detailed study of the geotechnical environment by a team of specialists from West Wallsend, Glencore’s other NSW and Queensland sites, and external consultants.

“We are not prepared to risk the safety of our employees by either continuing to mine LW46 or attempting to recover the longwall equipment.”

There is still potential for the remaining blocks to be extracted.

“We are continuing to review options for mining the two remaining approved longwalls (LW51 & 52) at West Wallsend.”

ICN has since heard some industry buzz that Glencore will relocate an unused existing longwall from another Glencore site. This includes that it will be trucked over from Queensland.

It is assumed that such an option was cheaper than using workers to manually dig out the buried longwall at West Wallsend – a task estimated by some to take six to eight weeks to complete.

ICN is seeking comment from Glencore regarding the longwall relocation speculation.

There are suspicions the collapse may have been linked to a fault in the workings.

West Wallsend mine won state government approval in October to mine two additional longwall panels, LW51 and LW52.

They equated to 2.55 million tonnes run of mine – a little less than the estimated 3Mt ROM the mine was no longer going to extract following the subsidence impacts the mine was blamed for in the Sugarloaf state conservation area.

At the time these two panels were considered enough to not alter West Wallsend’s existing mine life or approved production capacity of 5.5 million tonnes per annum ROM, with the panels selected after the adjacent Newstan colliery terminated a sublease.

However, Glencore has also considered market conditions when re-assessing West Wallsend’s mine life and decided to cease production in 2016.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production