MARKETS

Costs put squeeze on Pike River development

HIGHER steel and fuel costs and a declining NZ dollar has forced New Zealand Oil & Gas to increas...

Angie Tomlinson
Costs put squeeze on Pike River development

Of the new budget, $40 million was spent by September 30, 2006, leaving a balance of $104 million. The company said there would also be requirements for working capital of approximately $29 million for the period until full production is reached in 2009.

Pike River has already received, in August, new equity funds of $19.4 million net from Gujarat NRE Coke.

The $65 million project loan, of which $60 million is to be available for capital expenditures, has been sought from an Australasian bank and is currently subject to final documentation. These funds will be made available for the later stages of the development project.

It is intended that the $80 million to fund the remainder of the mine development costs as well as working capital will be met through new equity and the $20 million cash held by Pike River at September 30, 2006.

NZOG also reiterated its support for Pike River becoming separately listed on the New Zealand and Australian stock exchanges. The timing of the listing is still under consideration.

On the construction side, Pike River detonated the first round of explosives at the rock face at the entry point of the mine access tunnel on September 21, 2006.

The development’s main contractor, McConnell Dowell, mobilised to site during July/August 2006 and is now operating 24 hours per day, six days per week to excavate the 4.5m high by 5.5m wide tunnel, which will incline upwards for 2.3km to intersect with the Brunner seam coal reserves.

Work is also progressing on other facets of the mine development: the amenities area is being terraced and prepared for the construction of offices, stores and workshops; construction of the electrical substation at the coal preparation plant is well advanced with the first transformer due for delivery this month; all seven bridges and major culverts have been completed on the mine access road from Big River; and road surfacing, using rock from the tunnel excavation, has commenced.

The last 100m of road linking the two sections of road from the public road to the mine tunnel entry is expected to be completed in the next month.

Pike River also put in place a number of major contracts in the September 2006 quarter, including the contract for the supply of a roadheader and two continuous miners to develop the mine's roadways and the contract for the supply of the mine's underground electrical equipment.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production